40-B40454A Spring Garden Point Seawall and Park Restoration
This project is completed!
Project Photos
Project No.: 40-B40454A
Location: 601 NW 7th Street Road Miami, FL 33136
This project is located in District 5
Notice of Construction Work
The City of Miami will be renovating Spring Garden Park and the existing Seawall beginning on January 27, 2020. The contractor is David Mancini and Sons, Inc. Please note that once the renovations start, the park will close from January 27 to September 30. However, the North parcel will remain partially open.
Scope of Work
Seawall Installation and Park Restoration
Construction Cost
$1,389,000
Construction
Construction Modifications for this project is anticipated to commence on January 27 to September 30, 2020. Please note that this schedule could change due to adverse weather or other unexpected conditions.
Construction Schedule
Monday - Friday 8:00am to 5:00pm
Lane Closure
All efforts will be made to minimize the effects of the construction activities to area residents, schools, businesses and motorists.
Provide your feedback about this project here