Brickell Key Bridge Repairs 40-B193602
Brickell Key Bridge Rehabilitation/Repairs
Project is anticipated to start construction in 2025. Currently working on the project design.
SE 8th Street Brickell Key Drive, over Brickell Bay – Public Safety
Project Boundaries: From Brickell Key Drive to the end of Brickell Key Bridge, including the eastern side seawall
Scope of Work:
- Bridge Infrastructure (underdeck) and Seawall Repairs (east bridge supports – on Brickell Key side)
- Bridge Milling and Resurfacing
Rehabilitation and repairs of the Brickell Key Bridge will include:
- Full deck depth repairs at the beginning and end of the bridge
- Repair of the bridge drainage system and bridge surface repaving with new latex modified concrete (LMC) overlay
- Replacement of all expansion joints and asphalt replacement of the bridge approach slabs
- Inspection/repair of planters and support brackets, and repairs of the of the Brickell Key Bridge seawall
Estimated Project Cost: $6.6 M
Project Duration: Bridge repairs are to be done in two phases, with a duration of eight months (8) for both phases
Provide your feedback about this project