Ft. Dallas Park Selective Demo & Flagler Worker House Restoration
Project Scope of Work:
- Selective Demolition of Metal Buildings
- Tree protection
- Invasive vegetation removal
- Pavers reinstallation in disturbed areas
- Site pressure cleaning and site cleaning of all debris
- The Historic Restoration of the Flagler Worker's House
Project Boundaries:
Project Benefits:
This project will enhance the site conditions to move progressively to the Historic Restoration of the Flagler Worker's House.
Project Timeline:
- Metal Buildings Demolition (Phase I) = 3 months
- Historic Restoration Flagler Worker House (Phase II) = 18 months
How Will the Work be Performed?
- Phase I - Selective Demolition of Metal Buildings, tree protection, invasive vegetation removal, pavers reinstallation in disturbed areas, site pressure cleaning and site cleaning of all debris.
- Phase II - Historic Restoration Flagler Worker House