Mary Brickell Village & SW 1 Avenue Roadway & Drainage Improvements
Project is in its final construction stage.
June 2024
October 2023
Project during initial phases of construction (underground work)
Project No.: 40-B30637 & 40-B30833
Locations
SW/SE 9 Street from SW 1 Avenue to South Miami Avenue
SW/SE 10 Street from SW 1 Avenue to SE 1 Avenue (Brickell Plaza)
SW/SE 11 Street from SW 1 Avenue to South Miami Avenue
SW/SE 12 Street from SW 1 Avenue to South Miami Avenue
SW 1 Avenue from SE 7 Street to SW 15 Road
This project is Located in District 2
Notice of Construction Work
The City of Miami will be making much needed improvements and repairs during the next few months. Personnel and equipment from V. Engineering & Consulting Corp. will be working in your neighborhood during this time.
Scope of Work
Pavement Restoration
Drainage Improvements
New concrete sidewalks
New Curb and Gutter
Medians
New ADA ramps
Landscaping
Pavement markings
Signage
Construction Timeframe
Construction for this project is anticipated to commence in July 2019 and is anticipated to be completed by 2022. Please note that this schedule may be subject to change due to adverse weather or other unexpected conditions.
Estimated Construction Cost
$ 1,279,675
Contractor
V. Engineering & Consulting Corp.
Construction Hours
Monday through Friday, 8am to 5pm
Maintenance of Traffic (MOT)
Starting July 22, 2019 temporary traffic changes will be in place to ensure the work zone is safe during work. Motorist are asked to take extra care, keep to displayed speed limits and observe traffic controls and signage when traveling through work areas.
Construction is set to begin on SW 12 Street from SW 1 Avenue to South Miami Avenue.
If you have any questions or require additional information, please contact
us at askoci@miamigov.com or call (305) 416-1280
Office of Capital Improvements (OCI)… Building Better Neighborhoods and future for Miami.