Merrie Christmas Park Improvements
Work In Progress - February 2022
What?
Soil remediation and landscaping improvements to the left area of the playground (towards the Le Jeune Avenue side). Area is in the drawing below delimited by “limit work area”.
When?
Construction to start on Monday, Aug 9, 2021 and is anticipated to be completed by the end of January 2022. Schedule of construction hours is Monday - Friday 8:00am to 6:00pm.
How?
The park will remain open except for the area that will be fenced in for the work to be performed.