S. Bayshore Ln. & Fairview St. Roadway Improvements & New Pump Station

Miami-Dade-County-Logo.jpg Forever-Bond-Logo-002.png OCI-Rectangle-Logo-BEST.jpg

 

Project Number: 40-B30737

Click the tab below to view the South Bay Shore Lane Pump Station (Phase II) Presentation, shared at the May 16th, 2024 community meeting.

South Bayshore Lane Pumpstation - May 16th, 2024, Community Presentation

S. Bayshore Lane Pumpstation Phase II Presentation - Cover Page With Aerial Location Map

S. Bayshore Lane Pumpstation Phase II Presentation - Objectives Page

S. Bayshore Lane Pumpstation Phase II Presentation - Scope of Services

S. Bayshore Lane Pumpstation Phase II Presentation - Pumpstation Footprint Image

S. Bayshore Lane Pumpstation Phase II Presentation - Pump Station Footprint Plans Page

S. Bayshore Lane Pumpstation Phase II Presentation - Existing Utilities within Pump Station Footprint

S. Bayshore Lane Pumpstation Phase II Presentation - Elevated Platform Cross Section

S. Bayshore Lane Pumpstation Phase II Presentation - Elevated Platform for Pump Station Controls Rendering

S. Bayshore Lane Pumpstation Phase II Presentation - Sample Elevated Control Panel Platform Photo

S. Bayshore Lane Pumpstation Phase II Presentation - Drainage Plan

S. Bayshore Lane Pumpstation Phase II Presentation - Drainage Page 2

S. Bayshore Lane Pumpstation Phase II Presentation - Drainage Plan 3

S. Bayshore Lane Pumpstation Phase II Presentation - Outfall Design Considerations

 

Phase I - Completed in December 2020!

Phase I of this project included roadway and drainage Improvements on South Bayshore Lane and East/West Fairview Street. The scope of work included the following:

  • Roadway reconstruction
  • Drainage improvements, including a new watermain line replacement (done jointly with the Miami-Dade Water and Sewer Department) 
  • Damaged sidewalk replacement
  • Repair of driveway approaches
  • Swale restoration
  • Pavement marking, signage and ADA ramps

Phase II - Project Scope:

Design and construction of new stormwater pump station with a raised platform, two gravity drainage wells, a SCADA system, and upgrade to an existing outfall.

Project Cost Estimate:

$12,416,698

Project Benefits and Impacts:

The project will help alleviate localized flooding experienced by the community.

  • Number of properties impacted: Total = 96 (92 Residential and 4 Non-Residential)
  • Total property value protected: $118M 

Pump Station Location & Rendering:

Fairview Pump Station Map

South Bayshore Lane and Fairview Pump Station Location Rendering

South Bayshore Lane and Fairview Street Pump Station Rendering

Estimated Construction Timeline:

  • Estimated Construction Start: Winter 2025
  • Estimated Construction End: Winter 2027

Provide your feedback about this project here