Little Havana Pedestrian Priority Zone Planned Improvements in D3

School-Zone-Image-1.jpg

In 2021, City of Miami District 3 Commissioner Joe Carollo committed $2.5 million for the improvement, along with a $3M bipartisan bill sponsored by Senator Ileana Garcia and House Representative Michael Greico that passed in June 2021. In May 2022, the City of Miami Office of Capital Improvements developed the project scope and budget estimates to construct pedestrian safety improvements and have begun project design for priority one projects. 

Click here to download the Bilingual Little Havana PPZ Community Presentation that took place on Feb 15, 2023.(PDF, 6MB)

The City of Miami, in partnership with the State of Florida, is designing a plan to provide pedestrian safety in Little Havana in District 3.  The project will include various elements to improve the quality of life and provide pedestrian safety for school children, students and everyone in the community.

Project Number: 40-B213602

Project Scope:

Design and construction of pedestrian safety and greenway improvements and associated right-of-way improvements including sidewalks, ADA ramps, pedestrian crosswalks, planter islands, landscaping, lighting, milling and resurfacing, pavement markings, and related drainage relocations.

Project Cost Estimate:

$5,504,338

Project Benefits and Impacts:

  • Number of properties impacted: Total = 330 (171 Residential and 159 Non-Residential)
  • Total property value protected: $254M

Project Boundaries:

  • Zone 1 - NW 6 Street between NW 22 Avenue (excluding crossings) and NW 19 Avenue
  • Zone 2 - SW 10 Avenue between W Flagler Street (excluding Flagler Street, SW 1 Street intersections) and SW 5 Street. Intersections of: SW 2 Street and SW 9 Avenue, SW 2 Street and SW 11 Avenue, SW 2 Street and SW 13 Avenue.

Map indicating 40-B213602 Project Boundaries NW 6 ST.png

Map indicating 40-B213602 Project Boundaries SW 10 AV and Intersections.png

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Summer 2025
  • Estimated Construction End: Winter 2026

Provide your feedback about this project here