Golden Pines Roadway Improvements
Project Progress / December 2023
Project Benefits Include:
- New 8-inch water main
- New driveways, sidewalks and curbs
- New drainage system
- Pavement restoration
- Pavement markings
- Swale re-grading and sodding
Accomplishments – September/October 2023:
Click here to download the information flyers above.(PDF, 2MB)
SW 25th Street:
- Asphalt has been placed from SW 24th Terrace to SW 27th avenue.
- Driveways have been constructed west of 31st avenue.
- Concrete sidewalk should be completed on the project on 10-2-2023.
- Contractor will begin constructing driveways east of 31st avenue on 10-2-2023.
SW 24th Terrace:
- Concrete sidewalk has been completed throughout the project.
- Asphalt has been placed on SW 29th avenue and on SW 24th Terrace east of 29th avenue.
- Contractor will begin preparing to install valley gutter between SW 29th & 31st avenues on 10-2-2023, followed by finishing of lime rock base and placement of asphalt by 10-13-2023.
- Contractor will begin milling existing roadway to bring elevations to the top of subgrade on 10-2-2023, followed by the installation of the valley gutter by 10/13/2023.
Next Steps – Month of November 2023:
SW 25th Street:
More updates to come!
SW 24th Terrace:
More updates to come!
Provide your feedback about this project here