Legion Park Community Building Improvements, District 5
The City of Miami, District 5 Commissioner Christine King, the Department of Parks and Recreation,
and the Office of Capital Improvements proudly announce the reconstruction of the Legion Park Community Center!
Park Location: 6447 NE 7th Avenue, Miami, FL 33138
OCI Construction Status - July 2024
- Mechanical rough installation at 99%
- Electrical & plumbing rough completed
- Dry wall installation completed
- Roofing completed
- Elevator installation completed
- Installation of tiles in bathrooms completed
- Installation of terrazzo flooring completed. Pending polishing
- Purchase Order for replacement of HVAC equipment issued on 1/22/2024
- Units 1, 2 & 4 delivered on 4/23/2024. Heater for AHU 2 was delivered on 7/19/24.
- ACU's installation completed on 5/20/2024.
- Installation of Air Handlers began on 06/20/2024 (AHU's 1&2 in mechanical room 116).
- AHU #3 was delivered on 7/15/2024
- Next Actions: Installation of the remaining Air Handlers (3 & 4) scheduled for the week of 07/22/2024.
Substantial Completion date is scheduled for August 2024.
OCI Construction Status - April to May 2024
- Mechanical rough installation at 99% -- pending installation completion of air conditioning units
- Electrical & plumbing rough completed
- Dry wall installation completed
- Roofing completed
- Elevator installation completed -- pending polishing
- Installation of tiles in bathrooms is completed, as well as terrazzo flooring in the exterior bathroom area.
- Replacement HVAC equipment:
-
- Units 1, 2 & 4 delivered on 4/23/2024. Pending delivery of some items (thermostats, heaters, auxiliary drain pans, and legs for interior units AHU's).
- Delivery of Unit 3 is delayed - now it is scheduled for June 10
- Terrazzo installation on stairs to 2nd floor completed.
- Next Actions: HVAC installation began in May 2024. Compressors are installed. However, due to delay in the delivery of unit 3, the Project is now anticipated to be completed by August 2024.
Community Building - OCI Construction Status - January - March 2024
- Electrical rough installation completed
- Mechanical rough installation is at 99%
- Plumbing rough installation is completed
- Dry wall installation is completed
- Windows 2nd floor installation is completed
- Shingle Roofing is completed.
- Elevator installation is completed.
- Installation of tiles in the bathrooms is completed, as well as terrazzo flooring in the exterior bathroom area.
- Replacement of HVAC (new air conditioning) to be completed by the end of March 2024
Work in Progress - Working in Final Details:
New Roof Installation - Completed!
Interior Areas and Old Roofing - Initial work in progress:
New and improved elements in the building will include:
- Re-roofing of existing shingle roof (possibility of a clay barrel tile roof is being evaluated)
- Upgrade/remodel of bathrooms
- New warming kitchen
- Terrace repairs and new landscaping
- New elevator and fire alarm system
- New acoustical ceilings, interior layout modifications and replacement of selected doors and windows
- Second floor finishes and cabinetry
- Miscellaneous repairs of exterior walls
- Milling and resurfacing of existing parking lot and sidewalks repairs
- New tennis court and resurfacing of existing tennis court
While the building is in construction, a rental trailer will be available on-site to maintain the park’s programming for school children.
First Floor Design Plan and Materials (click here(PDF, 11MB) to download the PDF version of the image below)
Second Floor Design Plan (click here(PDF, 7MB) to download the PDF version of the image below)
Restroom Materials Details
Exterior Community Terrace
Side view of the Community Center
Click here(PDF, 1MB) to download the Legion Park Community Building Exterior Elevations document
Click here(PDF, 1MB) to download the Legion Park Community Building Site Plan document
Provide your feedback about this project here