SW 23 Street Roadway & Drainage Improvements
THIS PROJECT IS COMPLETE!
Project No.: B-173650
Location: SW 23 Street from SW 25 Avenue to SW 27 Avenue
This project is located in District 4
Notice of Construction Work
The City of Miami will be making much needed roadway improvements during the next few weeks. Personnel and equipment from Metro Express, Inc. will be working in your neighborhood during this time.
Scope of Work
The work consists of pavement restoration, drainage improvements, curb and gutter replacement, sodding and pavement markings.
Construction Cost
$178,515
Construction
Construction for this project is anticipated to commence in June 2019 and is anticipated to be completed by October 2019. Please note that this schedule could change due to adverse weather or other unexpected conditions.
Construction Schedule
All work will be carried out on week days between the hours of 8 am and
5 pm. There is no anticipated work on Saturdays or Sundays.
Lane Closure
All efforts will be made to minimize the effects of the construction activities to area residents, schools, businesses and motorist.