North Grapeland Heights Seawall


This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
February 2025.
Project Number: 40-B233813
Project Scope:
Design and construction of natural shoreline enhancements and associated improvements including dredging, rip-rap, guardrails, pavement milling and resurfacing, signage and pavement markings, and landscaping.
Project Cost Estimate:
$356,406
Project Benefits and Impacts:
- Number of properties impacted: Total = 3 Residential
- Total property value protected: $1.5M
Project Boundaries:
The project limits are bounded by NW 13 Street and NW 32 Avenue.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Summer 2026
- Estimated Construction End: Summer 2027