Spring Garden Neighborhood - Traffic Calming Project
Project Number: 40-B223601
Project Scope:
Design and construction of three traffic calming devices (2 raised intersections and 1 speed hump) and restriping of northbound lane approach at another intersection.
Project Cost Estimate:
$1,299,202
Project Benefits and Impacts:
- Number of properties impacted: Total = 167 (148 Residential and 19 Non-Residential)
- Total property value protected: $100M
Project Boundaries:
Raised Intersection at NW N River Dr and NW 10 Ct.
Raised Intersection at NW N River Dr and NW 9 Ct.
Speed Hump at NW 10 Ave between NW N River Dr and NW 11 St.
Intersection Improvement (left turning lane addition) at NW 9 Ct and NW 11 St.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Spring 2025
- Estimated Construction End: Winter 2026
Provide your feedback about this project here