Spring Garden Neighborhood - Traffic Calming Project

Project Number: 40-B223601

Project Scope:

Design and construction of three traffic calming devices (2 raised intersections and 1 speed hump) and restriping of northbound lane approach at another intersection.

Project Cost Estimate:

$1,299,202

Project Benefits and Impacts:

  • Number of properties impacted: Total = 167 (148 Residential and 19 Non-Residential)  
  • Total property value protected: $100M

Project Boundaries:

Raised Intersection at NW N River Dr and NW 10 Ct.

Raised Intersection at NW N River Dr and NW 9 Ct.

Speed Hump at NW 10 Ave between NW N River Dr and NW 11 St.

Intersection Improvement (left turning lane addition) at NW 9 Ct and NW 11 St.

Map indicating 40-B223601 Project Boundaries.png

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Spring 2025
  • Estimated Construction End: Winter 2026

Provide your feedback about this project here