Traffic Calming Devices NW 15 Ave between NW 7 Street and NW 9 Street

Project Number: 40-B243607

Project Scope:

Assessment of two locations for geometric fit for traffic calming device installations; balloting of one acceptable location; design and construction of one raised intersection at the eligible location.

Project Cost Estimate:

$871,638

Project Benefits and Impacts:

  • Number of properties impacted: Total = 4 Residential
  •  Total property value protected: $2M

Project Boundaries:

The project limits are bounded by

Location 1: NW 15 Ave and NW 8 Ter - Raised intersection (by City) and All-Way Stop Condition by MDC-DTPW.

Location 2: NW 15 Ave between NW 7 St and NW 8 St – Removed from project.

Map indicating 40-B243607 Project Boundaries.png

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Fall 2026
  • Estimated Construction End: Summer 2027

Provide your feedback about this project here