Auburndale Neighborhood Flood Improvements


This work was funded in part through a grant agreement from the Florida Department of Environmental Protection's Office of Resilience and Coastal Protection Resilient Florida Program. The views, statements, findings, conclusions, and recommendations expressed herein are those of the author(s) and do not necessarily reflect the views of the State of Florida or any of its subagencies.
December 2021.
Project Number: 40-B223802
Project Scope:
Design-build of stormwater infrastructure and associated roadway improvements including new and upsized stormwater inlets and pipes, exfiltration trenches, roadway reconstruction, milling and resurfacing, sidewalks and driveway approach repairs, concrete curbs and gutters, valley gutters, sidewalks, ADA ramps, signage and pavement markings, utility adjustments and harmonization; construction of a raised intersection at SW 32 Avenue and SW 2 Street. This project also includes a requested Joint Participation Agreement (JPA) with Miami-Dade Water and Sewer Department (MDWASD) for water main system betterments.
Project Cost Estimate:
$53,181,040
Project Benefits and Impacts:
The project will help alleviate localized flooding experienced by the community.
- Number of properties impacted: Total = 642 Total (583 Residential and 59 Non-residential)
- Total property value protected: $400M
Project Boundaries:
The project limits are bounded by SW 32nd Avenue to SW 37th Avenue, and West Flagler Street to SW 8th Street.
(PDF, 1MB)
Click the image above to download the pdf version.
Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Spring 2025
- Estimated Construction End: Summer 2027
Provide your feedback about this project here