Auburndale Traffic Device at SW 32 Avenue and SW 2 Street

Project Number: 40-B173655

Project Scope:

Design and construction of a raised intersection and associated and right-of-way improvements including roadway reconstruction, milling and resurfacing, ADA ramps, drainage system, pavement markings and signage.

Note: This project will be built under B-223802 Auburndale Neighborhood Flood Improvements.

Project Scope Estimate:

$1,335,790

Project Benefits and Impacts:

  • Number of properties impacted: Total = 4 Residential
  • Total property value protected: $1.6M

Project Boundaries:

The project limits are bounded by intersection of SW 32 Avenue and SW 2 Street.

Map indicating 40-B173655 Project Boundaries.png

Road Closures:

Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.

Estimated Construction Timeline:

  • Estimated Construction Start: Summer 2025
  • Estimated Construction End: Spring 2026

Provide your feedback about this project here