SW 24 Street from SW 27 Avenue to SW 32 Avenue

Miami-Forever-Bond-_1.png

Project Number: 40-B50413

Project Scope:

Design and construction of right-of-way improvements including driveway approaches, sidewalks, ADA ramps, valley gutters, curbs, drainage system, milling and resurfacing, roadway reconstruction, pavement markings and signage, swale regrading and sodding, and landscaping. This project also includes a Joint Participation Agreement (JPA) with the Miami-Dade Water and Sewer Department (MDWASD) for the installation of an 8-inch watermain, water service connections, and fire hydrants.

Project Cost Estimate:

$8,478,403

Project Benefits and Impacts:

  • Number of properties impacted: Total = 189 (113 Residential and 76 Non-Residential)
  • Total property value protected: $120M

Project Boundaries:

The project limits are bounded by 

Original: SW 24 Street between SW 27 Avenue and SW 32 Avenue.

Additional: SW 31 Avenue between SW 24 Street and SW 25 Street; SW 29 Avenue between SW 24 Terrace and SW 25 Street.

Map indicating 40-B50413 Project Boundaries.png

Estimated Construction Timeline:

  • Estimated Construction Start: Summer 2024
  • Estimated Construction End: Summer 2025

Provide your feedback about this project here