Buena Vista Local Drainage and Road Improvements

Project Number: 40-B233602
Project Scope:
Design and construction of right-of-way improvements including drainage system, partial roadway reconstruction, milling and resurfacing, sidewalks, curbs and gutters, landscaping, and lighting.
Project Cost Estimate:
$ 4,911,987
Project Benefits and Impacts:
The project will help alleviate localized flooding experienced by the community.
- Number of properties impacted: Total = 87 (56 Residential and 31 Non-residential)
- Total property value protected: $77M
Project Boundaries:
The project limits are bounded by NE 49 Street and NE 50 Street between North Miami Avenue and NE 2 Avenue.

Road Closures:
Some road closures may occur during construction but will be sequenced appropriately to minimize disruption to the residents.
Estimated Construction Timeline:
- Estimated Construction Start: Summer 2025
- Estimated Construction End: Winter 2026
Provide your feedback about this project here